Builder Must Respond To Homeowner’s Notice Of Claim Within 14 Days Even If Construction Defect Claim Is Not Alleged With The “Reasonable Detail” Required By California’s Civil Code – Blanchette v. Superior Court (2017) 8 Cal.App.5th 521

Richard H. Glucksman and David A. Napper | Chapman Glucksman | May 25, 2017

On February 10, 2017, California’s Fourth District Court of Appeal held that if a builder fails to acknowledge receipt of a homeowner’s Notice of Claim within 14 days, as required by the Right to Repair Act (“SB800”), specifically California Civil Code §913, the homeowner is released from the requirements of SB800 and may proceed with the filing of a lawsuit.

In Blanchette v. Superior Court, Blanchette owned 1 of 28 homes constructed by GHA Enterprises, Inc. (“GHA”). On February 2, 2016, Blanchette served GHA with notice of a claim, setting forth the alleged defects in all 28 homes. On February 23, 2016, GHA responded that the construction defects were not alleged with sufficient “reasonable detail” as required by Civil Code §910. In response, Blanchette asserted that GHA’s response was untimely and thus excused him and the other homeowners from any obligations under SB800.  The trial court found for the builder, GHA, holding that Blanchette’s Notice of Claim lacked detail sufficient to trigger GHA’s obligations under SB800.  Blanchette appealed the ruling.

Although the Court of Appeal agreed that Blanchette’s Notice of Claim was insufficient because it did not provide reasonable detail to satisfy Civil Code§910, the Court of Appeal held that GHA’s failure to timely acknowledge Blanchette’s Notice of Claim released Blanchette from the requirements of SB800.  As the Court of Appeal recognized, Civil Code §930 expressly provides that the timing requirements of SB800 are to be strictly construed.

The Court of Appeal reasoned that its holding is consistent with the purpose of SB800, which is to promote resolution of a homeowner’s construction defect claim “in an expeditious and non-adversarial manner.” The Court further reasoned that “[a]n interpretation that permits a builder to ignore the time limits of section 913 and nonetheless preserve its objection to the lack of detail in a notice and require that the trial court then resolve the issue after litigation has commenced, will only delay construction defect claims.”

Blanchette is a stark reminder that Courts will strictly enforce the tight and often unreasonable time frames set forth in SB800.  Accordingly, builders and their counsel must ensure proper compliance with the procedures and deadlines of SB800 in order to maintain their rights thereunder, including but not limited to, the right to challenge the sufficiency of a Notice of Claim served by a homeowner.

Leave a Reply

%d bloggers like this: