Minnesota Supreme Court Concludes Accrual Date of Claim Was Before End of Construction

Conor Shankman | Bernstein Shur Sawyer & Nelson PA | December 29, 2015

Can a statute of limitations start to run in a construction case before substantial completion? In a case from late November, the Minnesota Supreme Court answered the question in the affirmative.

For those who may not know, statutes of limitations are time limits which prevent parties from bringing stale actions or law suits to court. They are determined by the legislature and establish the maximum duration of time that can pass between the occurrence of an event that gives rise to a cause of action, and the filing of that law suit. A law suit brought after a governing statute of limitations has run is time-barred, forever, no matter how meritorious the cause of action may be.

In 328 Barry Avenue, LLC v. Nolan Properties Group, LLC, construction began on a three-story commercial building in Wayzata, Minnesota. In October of 2009, near the punch list phase of the project, water intrusion was discovered around a window elevation on the east side of the building. The owner believed the issue was remedied at that time, and the project was “substantially complete” in May of 2010. In August of 2010, however, there was further water intrusion in the same location, and efforts were undertaken throughout 2011 and 2012 to investigate the possible causes.

The building owner, 328 Barry Avenue, LLC, sued the general contractor in June of 2012. The general contractor argued that a two-year statute of limitations for actions in contract, tort, or otherwise to recover damages in an action related to real property barred the law suit. Under the statute, the cause of action accrued at the time of “discovery of the injury,” and the contractor argued that the owner “discovered” the injury in the fall of 2009. The trial court agreed and dismissed the action.

On appeal however, the owner argued that the statute of limitations “cannot be triggered prior to substantial completion of a construction project. . . . [because] discovery of a defect during construction is different than the discovery of an actionable injury and is therefore insufficient to trigger” the statute of limitations. Thus, the leaking observed in August of 2010 should be the accrual date, making the June 2012 filing timely under Minnesota law. The leaking that occurred back in 2009, claimed the owner, was something that the contractor could still fix as part of the construction project, and indeed, the owner believed that had happened.

The Minnesota Supreme Court said its only duty was…

To finish reading this article

Leave a Reply

%d bloggers like this: