New Mandatory Bond Notice Forms in Florida

Brian A. Wolf and Miles D. Jolley | Smith Currie & Hancock | November 18, 2019

Subcontractors and suppliers must now use new, statutory notice of nonpayment forms to preserve payment bond claims, and sign each notice of nonpayment under oath.

The State of Florida instituted changes to the statutes governing public-project payment bonds (section 255.05, Florida Statutes) and private-project payment bonds (section 713.23, Florida Statutes). The changes went into effect on October 1, 2019. Previously, notices of nonpayment were not required to be signed under oath. Now, the law requires the use of specific statutory notice forms that claimants must sign under oath. Previously, there were no statutory penalties for claimants who exaggerated the amount claimed against a payment bond. Now there are specific statutory penalties against a claimant who willfully or negligently signs a notice of nonpayment that includes a claim for work not performed or materials not furnished, or who is guilty of signing a notice prepared with willful or gross negligence.

Public construction payment bonds are governed by section 255.05, Florida Statues, also known as Florida’s Little Miller Act. This statute requires all payment bond claimants who don’t have a direct contract with the general contractor to serve both the bonding company and the general contractor with a notice of nonpayment no later than 90 days after their last date of work or last delivery of materials. The amended statute now requires that the claimant use the statutory notice form and sign the form under oath. If the claimant includes exaggerated claims, or intentionally makes a claim for work or materials not provided, or otherwise prepares a notice with gross negligence, then the bonding company and the general contractor will be able to use such as a complete defense to an otherwise valid bond claim.

Private construction payment bonds posted by the general contractor are governed by section 713.23, Florida Statutes. This statute requires all payment bond claimants including those contracting directly with the general contractor to serve both the bonding company and the general contractor with a notice of nonpayment no later than 90 days after their last date of work or last delivery of materials. The amended statute now requires that the claimant use the statutory notice form and sign the form under oath. If the claimant includes exaggerated claims, or intentionally makes a claim for work or materials not provided, or otherwise prepares a notice with gross negligence, then the bonding company and the general contractor will be able to use such as a complete defense to an otherwise valid bond claim. Another important change to section 713.23 is the new requirement that payment bond claimants specify the portion of their bond claim that represents retainage. Previously, the requirement to specify the amount claimed for retainage only applied to public projects — now it applies to both public and private projects.

The changes to Florida’s payment bond statutes are intended to deter and penalize claimants who make exaggerated or fraudulent bond claims. It should be anticipated that the courts will apply the revised statutes in the same manner as established law regarding fraudulent liens since the statutory changes are modeled after the Florida’s fraudulent lien statute, section 713.31, Florida Statutes. Claimants who previously used lien notice services or non-attorney collection companies to prepare their bond-claim notices should strongly consider using an experienced construction attorney to advise them regarding both liens and bond notices since the penalties for serving a false, exaggerated or negligently prepared notices are severe, and advice of legal counsel is a recognized defense to a fraudulent lien claim.

Leave a Reply

%d bloggers like this: