Katherine E. Kohm | The Dispute Resolver | June 23, 2016
Within the last month, two decisions with two outcomes were issued concerning “pay-if-paid” provisions. Observe that a “pay-if-paid” provision is a true condition precedent in that a general contractor is not required to pay its subcontractor unless and until it receives payment from the owner. A different result flows from a “pay-when-paid” provision which only allows the general contractor a reasonable time to pay the subcontractor after receiving payment from the owner, but the risk of non-payment from the owner is not shifted to the subcontractor.
In Midlantic Fire, LLC v. Ernest Bock & Sons, Inc., No. DC–8529–14, 2016 WL 3093075, at *1 (N.J.Super. Ct. June 3, 2016), the pay-if-paid clause stated:
Payment by Owner to the General Contractor for the work/materials invoiced by the Subcontractor/Supplier shall be a condition precedent to General Contractor’s obligation to pay Subcontractor/Supplier. Accordingly Subcontractor/Supplier agrees and understands that it shall bear the risk of non-payment by the Owner and shall be entitled to no compensation from the General Contractor in the event of non-payment by the Owner for its work/materials.
Applying Pennsylvania law, per the contract, the court affirmed in favor of the subcontractor because “courts are reluctant to enforce a conditional payment provision against an unpaid subcontractor that is not responsible for the condition giving rise to the payment defense” and because “parties to a contract have an implied duty not to frustrate conditions precedent to their performance” (citing Quinn Constr., Inc. v. Skanska USA Bldg., Inc., 730 F. Supp.2d 401, 420 (E.D.Pa.2010)). Because the subcontractor had relied on the plans and drawings submitted by the general contractor and therefore because all coordination among subcontractors was the general contractor’s responsibility, the subcontractor was not responsible for the non-payment. Rather the defendant general contractor’s own error spurred the need for the change order and the owners refusal to pay the change order. As such, the pay-if-paid provision was inapplicable and the general was required to pay the subcontractor.
In A. Zahner Company v. McGowan Builders, Inc., No. WD 78063, 2016 WL 2994022, (Mo.App. Ct May 24, 2016), the pay-if-paid stated:
[Subcontractor] agrees that [the general contractor] will not be responsible to make any payment, progress or final, to [subcontractor] for any and all of the goods identified in this Purchase Order unless and until [general contractor] receives payment for such goods from the Owner of the project . . . . If Subcontractor is not paid within 45 days of when a pay application is submitted, Subcontractor may stop the Work of this Subcontract until payment is received . . . .