Nevada’s Common Law Meaning of the Term “Substantial Completion” in the Statute of Repose

William Doerler | The Subrogation Strategist Statutes of repose establish a legislature’s determination of when defendants should be free from liability. As set forth in Nevada Revised Statute (NRS) 11.202, the statute of repose for construction improvements in Nevada is six years after “substantial completion.” In Somersett Owners Ass’n v. Somersett Dev. Co., 492 P.3d 534… Continue reading Nevada’s Common Law Meaning of the Term “Substantial Completion” in the Statute of Repose

Ohio Appellate Court Awards Consequential Damages for Contractor’s Failure to Achieve Substantial Completion Due to Recklessness

Alexandra Parriman | Bricker & Eckler When a contractor indicated indifference to executing a project on schedule and failing to meet the substantial completion date, an Ohio appellate court found that the contractor’s actions constituted recklessness and, based on the terms of the contract, triggered the award of consequential damages. This case arose out of a contract… Continue reading Ohio Appellate Court Awards Consequential Damages for Contractor’s Failure to Achieve Substantial Completion Due to Recklessness

Parties’ Agreement Doesn’t Pull the Trigger on California’s Statute of Repose

William Boerler | The Subrogation Strategist In Hensel Phelps Constr. Co. v. Superior Court, 257 Cal. Rptr. 3d 746 (Cal. Ct. App. 2020), the Court of Appeals of California, Fourth Appellate District, addressed whether a party’s contractual definition of the phrase “substantial completion” controlled the trigger date for California’s construction-related statute of repose, Cal. Civ. Code… Continue reading Parties’ Agreement Doesn’t Pull the Trigger on California’s Statute of Repose

Contract’s Definition of “Substantial Completion” Does Not Apply to Third Party for Purposes of SOL, Holds Court of Appeal

Garret Murai | California Construction Law Blog Those of you in the construction industry know that the two primary statutes of limitation are the 4-year year statute of limitations for patent defects and 10-year statute of limitations for  latent defects. Both statutes begin to run on “substantial completion.” In Hensel Phelps Construction Co. v. Superior Court… Continue reading Contract’s Definition of “Substantial Completion” Does Not Apply to Third Party for Purposes of SOL, Holds Court of Appeal

Construction Law – What to Know About Substantial Performance

J. Norman Stark | December 12, 2016 In every construction contract and construction project, the term “substantial performance” is frequently referred to as “substantial completion”. This term, derived from custom and judicial precedent, rather than statutes, provides that when the work has been completed, even imperfectly, such performance warrants payment. In construction claims, most legal… Continue reading Construction Law – What to Know About Substantial Performance

%d bloggers like this: